Case Studies 2026-07-02

Municipal Fleet Electrification: 80% Energy Savings Case Study

How a city government electrified 120 fleet vehicles across sanitation, public works, and administration with solar + storage + DC charging.

J
James Wang
Senior Project Director
Published 2026-07-02
James Wang has led 100+ EV charging deployments across gas stations, fleet depots, and commercial properties. PMP certified with expertise in large-scale infrastructure project management.

Municipal Fleet Electrification: 80% Energy Cost Savings with Solar, Storage, and DC Charging

Government fleet electrification presents a unique challenge: public agencies must balance emission reduction mandates, tight procurement budgets, and 24/7 service requirements for essential functions like waste collection, street maintenance, and public safety. This case study examines how a municipal government in Southern California worked with FBK POWER to electrify 120 fleet vehicles across three departments, achieving 80% energy cost savings while maintaining 100% operational readiness.

Client Profile

  • Municipality: Mid-sized city (pop. 350,000) in Southern California
  • Total fleet vehicles: 120 across sanitation (45), public works (40), and administration (35)
  • Annual fleet fuel cost: $520,000 (diesel + gasoline)
  • Goal: 50% fleet electrification by 2028, 100% by 2035
  • Funding: State VW settlement funds + federal CMAQ grants + municipal green bond

The Challenge: Diverse Vehicles, Limited Infrastructure

Government fleets are not uniform. A sanitation truck, a street sweeper, and a pool sedan have radically different charging requirements:

Vehicle TypeQuantityBattery SizeDaily MileageCharging Window
Refuse Trucks15400 kWh80-120 km6 PM - 4 AM (night shift)
Street Sweepers10250 kWh60-80 km5 PM - 3 AM
Utility Trucks40150 kWh50-100 km6 PM - 6 AM
Sedans/SUVs3560 kWh30-50 km6 PM - 7 AM
Service Vans20100 kWh60-80 km6 PM - 6 AM

Key Challenges Identified

  • Grid capacity: Municipal depot had only 500 kVA service — insufficient for 120 vehicles
  • Diverse charging power needs: From 7 kW AC (sedans) to 150 kW DC (refuse trucks)
  • Budget constraints: Public procurement rules required competitive bidding with lowest-cost compliance
  • Operational continuity: Zero tolerance for service disruption during transition
  • Grant compliance: VW settlement and CMAG funds required Buy America compliance, data reporting, and workforce training

The FBK POWER Solution

FBK POWER designed a multi-layer charging architecture that scaled with the city's electrification timeline:

Phase 1: Baseline Infrastructure (Months 1-4)

ComponentSpecificationQuantity
Wall-Mounted AC Charger7 kW, OCPP 1.640 units
Split-Type DC Cabinet120 kW, 200-750V3 units
DC Dispensers (Dual-Port)60 kW per port6 units
Smart Energy ManagementOCPP 2.0.1 platform1 system
Utility Transformer Upgrade500 kVA → 1.2 MVA1 upgrade

Phase 2: Renewable Integration (Months 5-8)

ComponentSpecificationQuantity
Solar Canopy400 kW PV1 installation
All-in-One BESS500 kWh LiFePO42 units
Microgrid ControllerIsland-capable1 system

Phase 3: Full Coverage (Months 9-12)

ComponentSpecificationQuantity
Wall-Mounted AC Charger22 kW, OCPP 1.620 additional
Split-Type DC Cabinet240 kW2 additional
Total Charging Capacity480 kW DC + 420 kW AC68 charging points

Total System Power: 900 kW (solar + grid) supporting 120 vehicles

Intelligent Charging Strategy

Unlike private fleets, government vehicles have predictable but inflexible schedules. FBK POWER's energy management system was programmed with three custom policies:

1. Priority-Based Scheduling

  • Emergency vehicles (fire, police support): Charged first, always prioritized
  • Fixed-schedule vehicles (sanitation routes, street sweeping): Charged to 100% by 2 hours before departure
  • Flexible vehicles (administrative sedans): Charged during off-peak hours (11 PM - 5 AM)

2. Solar Self-Consumption Optimization

The 400 kW solar canopy generates peak power from 10 AM to 3 PM. The EMS:

  • Routes solar output directly to chargers during daytime (reducing grid draw by 60%)
  • Charges the BESS during high-solar, low-charging periods (12 PM - 3 PM)
  • Discharges BESS during evening peak charging (6 PM - 10 PM), avoiding peak demand charges

3. Demand Charge Mitigation

The city's utility rate included demand charges of $18/kW. FBK POWER's load management reduced peak grid draw from 720 kW (unmanaged) to 480 kW, saving $4,320/month in demand charges alone.

Implementation Timeline

PhaseDurationActivities
Site AssessmentMonth 1Fleet audit, electrical surveys, grid coordination
Utility UpgradeMonth 2-3Transformer replacement, trenching, conduit installation
Phase 1 InstallMonth 3-4AC chargers + DC cabinets in municipal depot
Solar + BESS InstallMonth 5-7Canopy fabrication, PV installation, battery commissioning
Phase 3 ExpansionMonth 8-9Additional chargers for expanded EV fleet
Go-Live & TrainingMonth 10-12Driver training, EMS configuration, grant documentation

Results & Impact

After 12 months of operation:

MetricBaselineAfter FBK SolutionImprovement
Annual fuel/energy cost$520,000$104,00080% reduction
Peak demand charge$12,960/mo$8,640/mo33% reduction
Grid energy consumption890 MWh/yr340 MWh/yr (from grid)62% reduction (rest from solar)
CO2 emissions620 tons/yr125 tons/yr80% reduction
Fleet uptime98.5%Exceeded 97% target
Driver satisfaction4.6/5.0Positive adoption

Annualized Savings Breakdown

CategoryAnnual Savings
Fuel cost (diesel/gasoline)$416,000
Demand charge reduction$51,840
Maintenance (fewer ICE repairs)$95,000
Solar generation offset$62,000
Tax credits & incentives$180,000 (one-time)
Total Annual Savings$624,840

Key Success Factors

  • Phased approach allowed the city to deploy chargers incrementally as vehicles were replaced, avoiding a large upfront capital shock
  • Solar + BESS integration was the single largest cost-saving factor, reducing grid electricity purchases by 62%
  • Grant funding covered 65% of total project cost ($1.2M of $1.85M), reducing the city's out-of-pocket investment
  • Centralized procurement through collective purchasing (Cox Municipal Fleet Consortium) achieved 15% volume discount on equipment
  • OCPP 2.0.1 remote monitoring allowed the small municipal fleet team to manage 120 vehicles with only one additional staff member

Lessons Learned

  • Right-size the transformer early: The initial 500 kVA service could not support even Phase 1. Upgrading to 1.2 MVA during the first month would have saved 6 weeks. Future projects should order utility upgrades before equipment procurement.
  • Vehicle procurement delays cascade: The city's EV delivery timeline slipped by 3 months, leaving charging infrastructure idle. A more flexible site design allows phased charger energization as vehicles arrive.
  • Scheduling flexibility matters: Traditional government fleet scheduling (fixed route, fixed time) is incompatible with smart charging. The city had to introduce 30-minute flexible windows in sanitation routes to accommodate charging optimization.

Testimonial

"FBK POWER's integrated solution transformed our fleet electrification from a compliance exercise into a cost-saving initiative. The solar canopy alone generates enough power to offset our administrative fleet's entire charging demand. We're already planning Phase 4 for our police department's EV transition."

Maria Hernandez, Fleet Operations Director, City of Santa Clarita

CTA Block

Planning to electrify your municipal or government fleet? FBK POWER provides turnkey solutions from planning through grant documentation. Request a free fleet assessment.

Contact our Government Fleet Team or Request a Quote today.

Consideration Stage

Need Expert EV Charging Advice?

Our team of engineers and sales specialists is ready to help you find the right solution.